The National Capital Planning Commission (NCPC) will consider final site and building plans for a new monumental arch at Memorial Circle on November 5, 2026. The U.S. Department of the Interior submitted the project, which the applicant says would celebrate the triumphs of the American people as part of the Semiquincentennial. The arch would rise about 250 feet from its base to the top of its statuary, at the western end of Arlington Memorial Bridge.
For business, the vote matters for three reasons. It is the last NCPC approval for one of the largest building projects tied to the 250th anniversary. Construction would run well beyond 2026. And the plans change traffic patterns at a busy Potomac River crossing next to Arlington National Cemetery.
Where the review stands
NCPC commented on concept plans on June 4 and approved preliminary plans on July 9, with comments to be addressed before final review. In July, commissioners said they were still considering whether the Height of Buildings Act is binding on the federal government, and that they would need to decide that question before final action. They asked the applicant for a height justification and for details on traffic, loading, aviation lighting and the final granite cladding.
The November submission on NCPC’s project page includes a Height of Buildings Act justification, a lighting plan, final renderings and environmental documents. According to NCPC’s project synopsis, the Federal Aviation Administration issued a determination of no hazard to air navigation on September 18, and the National Park Service (NPS) signed a finding of no significant impact (FONSI) on October 9. The FONSI states that it is not the final decision. NPS will issue a separate decision document after NCPC’s review.
Historic preservation comments
The Advisory Council on Historic Preservation (ACHP) ended Section 106 consultation on September 24, judging that further talks were unlikely to produce an agreement. In an October 9 letter to Interior Secretary Doug Burgum, the council said NPS had identified adverse effects on six National Historic Landmarks, eight historic districts, eight cultural landscapes and 20 other properties. It said NPS received about 107,000 public comments.
The council asked Interior to explain how the project serves the public interest despite those effects, and how the final decision reflects its comments and public views. NCPC’s synopsis says the Secretary’s response concludes the Section 106 process.
Construction and traffic
The FONSI expects about two to three years of construction, year-round, in two 10-hour shifts a day. It lists seven phases, from site excavation to site restoration. Mitigation includes noise blankets around pile driving, stormwater controls, and detours with signs and wayfinding.
The final plans remove two northbound movements on Washington Boulevard at the circle: the through movement and the turn onto Memorial Avenue. Memorial Avenue would carry curbside space for pickup, drop-off and bus loading. The synopsis says coordination with the U.S. Department of Transportation, Arlington County and Arlington National Cemetery is ongoing.
The planning documents reviewed for this article do not state the project’s cost or funding source.
What to watch
The next steps are NCPC’s position on the height question, its vote on final plans and the NPS decision document. Organizations with offices, contracts or events near the Memorial Bridge corridor will want to follow the construction schedule and detour plans as they are published.
Sources
- National Capital Planning Commission: Project 8778, New Monumental Arch (review history and materials)
- National Capital Planning Commission: Updated project synopsis, November 5, 2026 meeting (PDF)
- National Park Service: Finding of No Significant Impact, Triumphal Arch (PDF)
- Advisory Council on Historic Preservation: Letter to the Secretary of the Interior, October 9, 2026 (PDF)